Amendment 132 #
Proposal for a regulation
Recital 5
(5) In the past, electricity customers were purely passive, often buying electricity at regulated prices which had no direct relation to the market. In the future, customers need to be enabled to fully participate in the market on equal footing with other market participants and be empowered to manage their energy consumption. To integrate growing shares of renewable energy, the future electricity system should make use of all available sources of flexibility, particularly demand response and storage and of digitalisation through the integration of innovative technologies with the electricity system. To achieve effective decarbonisation at lowest cost, it also needs to encourage energy efficiency.
2017/09/25
Committee: ITRE
Amendment 145 #
Proposal for a regulation
Recital 11
(11) Derogations to fundamental market principles such as balancing responsibility, market-based dispatch, or curtailment and redispatch reduce flexibility signals and act as barriers to the development of solutions such as storage, demand response or aggregation. WhileBroad derogations are still neccovering entire technologiess ary to avoid unnecessary admie not consistent with the objective of achieving market-based and efficient decarbonistrative burden for certain actors, in particular households and SMEs, broad derogations covon and should therefore only be maintained for installations that were benefiting from these derogations before the entering eintire technologies are not consistent with the objective of achieving market-based and efficient decarbonisation and should thus be replaced by more targeted measureso force of this Regulation in order to avoid the negative impact of retroactivity measures. Member states should at the same time ensure full access to all market participants to competitive balancing markets and high transparency of curtailment and redispatch measures in order for the energy market to function.
2017/09/25
Committee: ITRE
Amendment 188 #
Proposal for a regulation
Recital 36
(36) Regional operational centres should primarily act in the interest of system and market operation of the region over the interests of any single entity. Hence, regional operational centres should be entrusted with decision-making powers to act and to direct actions to be taken by transmission system operators of the system operation region for certain functions and with an enhanced advisory role for the remaining functions. Regional operational centres should ensure that decision-making processes are based on equitable treatment, geographical balance and inclusiveness, in order to ensure the representation of all transmission systems of the region.
2017/09/25
Committee: ITRE
Amendment 193 #
Proposal for a regulation
Recital 38
(38) In order to raise efficiencies in the electricity distribution networks in the Union and ensure close cooperation with transmission system operators and ENTSO for electricity, a European entity of distribution system operators in the Union ("EU DSO entity") should be established. The tasks of the EU DSO entity should be well-defined and its working method should ensure efficiency, transparency, independence and representativeness amongst the Union distribution system operators. The EU DSO Entity should closely cooperate with ENTSO for Electricity on the preparation and implementation of the network codes where applicable, on the need for standardisation to facilitate crossborder data exchange between transmission system operators and distribution system operators, and should work on providing guidance on the integration inter alia of distributed generation and storage in distribution networks or other areas which relate to the management of distribution networks.
2017/09/25
Committee: ITRE
Amendment 232 #
Proposal for a regulation
Article 2 – paragraph 2 – point u
(u) 'capacity mechanism' means an temporary administrative measure to ensure the achievement of the desirednecessary level of security of supply by remunerating resources for their availability not including measures relating to ancillary services;
2017/09/25
Committee: ITRE
Amendment 245 #
Proposal for a regulation
Article 2 – paragraph 2 – point v
(v) 'strategic reserve' means a capacity mechanism in which resources are excluded from the market and only dispatched in case day-ahead and intraday markets have failed to clear, transmission system operators have exhausted their balancing resources to establish an equilibrium between demand and supply, and imbalances in the market during periods where the reserves were dispatched are settled at the value of lost load;
2017/09/25
Committee: ITRE
Amendment 264 #
Proposal for a regulation
Article 3 – paragraph 1 – point c
(c) customers shall be enabled to benefit from market opportunities and increased competition on retail markets and be empowered to act as participant in the energy market and the energy transition;
2017/09/25
Committee: ITRE
Amendment 330 #
Proposal for a regulation
Article 4 – paragraph 2 – point a
(a) demonstration projects;deleted
2017/09/25
Committee: ITRE
Amendment 332 #
Proposal for a regulation
Article 4 – paragraph 2 – point b
(b) generating installations using renewable energy sources or high- efficiency cogeneration with an installed electricity capacity of less than 500 kW;deleted
2017/09/25
Committee: ITRE
Amendment 351 #
Proposal for a regulation
Article 4 – paragraph 3
3. From 1 January 2026, point (b) of paragraph 2 shall apply only to generating installations using renewable energy sources or high-efficiency cogeneration with an installed electricity capacity of less than 250 kW.deleted
2017/09/25
Committee: ITRE
Amendment 355 #
Proposal for a regulation
Article 4 – paragraph 3 a (new)
3a. For the purpose of paragraph 1, Member states shall ensure that all market participants have access to competitive balancing markets and services for the delegation of their balancing responsibility and other flexibility services that are cost-reflective, and provide fair value for balancing.
2017/09/25
Committee: ITRE
Amendment 366 #
Proposal for a regulation
Article 5 – paragraph 1
1. All market participants shall have full access to the balancing market, be it individually or through aggregation. Balancing market rules and products shall respect the need to accommodate increasing shares of variable generation as well as increased demand responsiveness and the advent of new technologies.
2017/09/25
Committee: ITRE
Amendment 398 #
Proposal for a regulation
Article 5 – paragraph 8
8. The procurement of balancing capacity shall be facilitated cross-border and on a regional level in accordance with point 8 of Annex I. The procurement shall be based on a primary market and organised in such a way as to be non- discriminatory between market participants in the prequalification process individually or through aggregation.
2017/09/25
Committee: ITRE
Amendment 412 #
Proposal for a regulation
Article 5 – paragraph 10 a (new)
10a. Member States shall report on the functioning and transparency of, and access, in particular by small providers, to, the balancing markets, in particular for the purpose of Article 4, through the reporting procedure on the internal energy market laid down in Article 21 of Regulation .../... [Governance of the Energy Union].
2017/09/25
Committee: ITRE
Amendment 441 #
Proposal for a regulation
Article 7 – paragraph 4
4. By 1 January 2025, the imbalance settlement period shall be 15 minutes or less in all control areas.
2017/09/25
Committee: ITRE
Amendment 467 #
Proposal for a regulation
Article 9 – paragraph 1
1. There shall be no maximum limit of the wholesale electricity balancing market price unless it is set at the value of lost load as determined in accordance with Article 10. There shall be no minimum limit of the wholesale electricity balancing market price unless it is set at a value of minus 2000 € or less and, in the event that it is or anticipated to be reached, set at a lower value for the following day. This provision shall apply, inter alia, to bidding and clearing in all timeframes and include balancing energy and imbalance prices.
2017/09/25
Committee: ITRE
Amendment 477 #
Proposal for a regulation
Article 10 – paragraph 1
1. By [OP: one year after entry into force] Member Sstates shall establish a single estimate of the Value of Lost Load (VoLL) for their territory, expressed in €/MWh. That estimateIn case of cross-border bidding zones, Member states shall establish a common estimate of the VoLL. These estimates shall be reported to the Commission and made publically available. Member States may establish different VoLL per bidding zone if they have several bidding zones in their territory. In establishing VoLL, Member States shall apply the methodology developed pursuant to Article 19(5).
2017/09/25
Committee: ITRE
Amendment 490 #
Proposal for a regulation
Article 11 – paragraph 1
1. Dispatching of power generation facilities and demand response shall be transparent, non-discriminatory and market based unless otherwise provided under paragraphs 2 to 4.
2017/09/25
Committee: ITRE
Amendment 492 #
Proposal for a regulation
Article 11 – paragraph 2
2. When dispatching electricity generating installations, transmission system operators shall give priority to generating installations using renewable energy sources or high-efficiency cogeneration from small generating installations or generating installations using emerging technologies to the following extent: (a) generating installations using renewable energy sources or high- efficiency cogeneration with an installed electricity capacity of less than 500 kW; or (b) demonstration projects for innovative technologies.deleted
2017/09/25
Committee: ITRE
Amendment 530 #
Proposal for a regulation
Article 11 – paragraph 3 – subparagraph 1
Where the total capacity of generating installations subject to priority dispatch under paragraph 2 is higher than 15 % of the total installed generating capacity in a Member State, point (a) of paragraph 2 shall apply only to additional generating installations using renewable energy sources or high-efficiency cogeneration with an installed electricity capacity of less than 250 kW.deleted
2017/09/25
Committee: ITRE
Amendment 537 #
Proposal for a regulation
Article 11 – paragraph 3 – subparagraph 2
From 1 January 2026, point (a) of paragraph 2 shall apply only to generating installations using renewable energy sources or high-efficiency cogeneration with an installed electricity capacity of less than 250 kW or, if the threshold under the first sentence of this paragraph has been reached, of less than 125 kW.deleted
2017/09/25
Committee: ITRE
Amendment 551 #
Proposal for a regulation
Article 11 – paragraph 4
4. GBy way of derogation from paragraph 1, generating installations using renewable energy sources or high- efficiency cogeneration which have been commissioned prior to [OP: entry into force] and have, when commissioned, been subject to priority dispatch under Article 15(5) of Directive 2012/27/EU of the European Parliament and of the Council or Article 16(2) of Directive 2009/28/EC of the European Parliament and of the Council35 shall remain subject to priority dispatch. Priority dispatch shall no longer be applicable from the date where the generating installation is subject to significant modifications, which shall be the case at least where a new connection agreement is required or the generation capacity is increased. _________________ 35 Directive 2009/28/EC of the European Parliament and of the Council of 23 April 2009 on the promotion of the use of energy from renewable sources and amending and subsequently repealing Directives 2001/77/EC and 2003/30/EC (OJ L 140, 5.6.2009, p. 16).
2017/09/25
Committee: ITRE
Amendment 575 #
Proposal for a regulation
Article 12 – paragraph 3
3. The responsible system operators shall report at least once per year to the competent regulatory authority, which shall be transmitted to the Agency, on curtailment or downward redispatching of generating installations using renewable energy sources or high-efficiency cogeneration and on measures taken to reduce the need for such curtailment or downward redispatching in the future, including investments in digitalisation of the grid infrastructure and in services that increase flexibility. Curtailment or redispatching of generating installations using renewable energy sources or high- efficiency cogeneration shall be subject to compensation pursuant to paragraph 6.
2017/09/25
Committee: ITRE
Amendment 685 #
Proposal for a regulation
Article 13 – paragraph 6
6. Where further bidding zone reviews are launched under Article 32(1)(a), (b) or (c) of Regulation (EU) 2015/1222, the Commission may adopt a decision within six months of the conclusion of that bidding zone review.deleted
2017/09/25
Committee: ITRE
Amendment 730 #
Proposal for a regulation
Article 16 – paragraph 1
1. Charges applied by network operators for access to networks , including charges for connection to the networks, charges for use of networks, and, where applicable, charges for related network reinforcements, shall be fair, cost- reflective, transparent, take into account the need for network security and flexibility and reflect actual costs incurred insofar as they correspond to th, recover allowed total coset of an efficient and structurally comparable network operatorproviding the regulated services, and are applied in a non-discriminatory manner. In particular, they shall neutrally support overall system efficiency in the long run through price signals to consumers and producers and they shall as far as possible be applied in a way which does not discriminate between production connected at the distribution level and production connected at the transmission level, either positively or negatively. They shall not discriminate against energy storage and shall not create disincentives for participation in demand response. Without prejudice to paragraph 3, those charges shall not be distance- related.
2017/09/25
Committee: ITRE
Amendment 738 #
Proposal for a regulation
Article 16 – paragraph 2
2. Tariffs shall grant appropriate incentives to transmission and distribution system operators, over both the short and long term, to increase efficiencies, including energy efficiency, foster market integration and security of supply, and support efficient investments, in particular in digitalisation, flexibility services and interconnections, and the related research activities .
2017/09/25
Committee: ITRE
Amendment 761 #
Proposal for a regulation
Article 16 – paragraph 7
7. Distribution tariffs shall reflect the cost and benefits of use of the distribution network by system users including active customers, and may be differentiated based on system users’ consumption or generation profiles. Where Member States have implemented the deployment of smart metering systems, regulatory authorities mayshall introduce time differentiated network tariffs, reflecting the use of the network, in a transparent and foreseeable way for the consumer.
2017/09/25
Committee: ITRE
Amendment 771 #
Proposal for a regulation
Article 16 – paragraph 8
8. Regulatory authorities shall provide incentives to distribution system operators to procure services for the operation and development of their networks and integrate innovative solutions in the distribution systems. For that purpose regulatory authorities shall recognise as eligible and include all relevant costs in distribution tariffs and introduce performance targets in order to incentivise distribution system operators to raise efficiencies, including energy efficiency, digitalisation and flexibility, in their networks.
2017/09/25
Committee: ITRE
Amendment 778 #
Proposal for a regulation
Article 16 – paragraph 9 – introductory part
9. By [OP: please add specific date – three months after entry into force] the Agency shall provide a recommendation addressed to regulatory authorities on the progressive convergenceharmonisation of transmission and distribution tariff methodologies. That recommendation shall address at least:
2017/09/25
Committee: ITRE
Amendment 934 #
Proposal for a regulation
Article 20 – paragraph 1
1. When applying capacity mechanisms Member States shall have a reliability standard in place indicating their desired level of security of supply in a transparent manner. In case of cross- border bidding zones, such reliability standards shall be established jointly by the relevant authorities.
2017/09/25
Committee: ITRE
Amendment 1131 #
Proposal for a regulation
Article 27 – paragraph 1 – point new (h a (new)
new (h a) standardisation, in cooperation with the EU DSO entity, of relevant data formats and protocols to facilitate crossborder exchange of data ;
2017/09/25
Committee: ITRE
Amendment 1201 #
Proposal for a regulation
Article 34 – paragraph 1 – point h
(h) facilitate the crossborder and regional procurement of balancing capacity;
2017/09/25
Committee: ITRE
Amendment 1235 #
Proposal for a regulation
Article 35 – paragraph 1 – point b
(b) a procedure for consulting, in an efficient and inclusive manner, the transmission system operators of the system operation region in the exercise of its operational duties and tasks, in accordance with Article 37;
2017/09/25
Committee: ITRE
Amendment 1238 #
Proposal for a regulation
Article 35 – paragraph 1 – point c
(c) a procedure for the adoption of decisions and recommendations in accordance with Article 38 that ensures equitable treatment between members of the regional operational centre ;
2017/09/25
Committee: ITRE
Amendment 1248 #
Proposal for a regulation
Article 36 – paragraph 1
1. Regional operational centres shall develop working arrangements that are efficient, inclusive, and facilitate consensus, to address planning and operational aspects related to the functions to be performed, taking into account, in particular, the specificities and requirements of those functions as specified in Annex I.
2017/09/25
Committee: ITRE
Amendment 1260 #
Proposal for a regulation
Article 38 – paragraph 1
1. Regional operational centres shall develop a procedure for the adoption of decisions and recommendations, that ensures geographically balanced representation and equitable treatment between members of the Regional operational centre.
2017/09/25
Committee: ITRE
Amendment 1307 #
Proposal for a regulation
Article 40 – paragraph 2 a (new)
2 a. The Management board shall ensure that the functioning of the Regional operational centre is inclusive, ensures geographically- balanced representation and equitable treatment in the procedures and decision-making processes between members of Regional operational centre.
2017/09/25
Committee: ITRE
Amendment 1311 #
Proposal for a regulation
Article 40 – paragraph 3 – point d
(d) developing and endorsing the cooperative and inclusive decision-making processes in accordance with Article 35.
2017/09/25
Committee: ITRE
Amendment 1325 #
Proposal for a regulation
Article 42 – paragraph 1
Regional operational centres shall be equipped with all the human, technical, physical and financial resources necessary for fulfilling their obligations under this Regulation and carrying out their functions, ensuring in particular geographically balanced representation and equitable treatment between members of Regional operational centre.
2017/09/25
Committee: ITRE
Amendment 1355 #
Proposal for a regulation
Article 47 – paragraph 4
4. Transmission system operators shall publish relevant data on aggregated forecast and actual demand, on availability and actual use of generation and load assets, on availability and use of the networks and interconnections, and on balancing power and reserve capacity and on the availability of flexibility. For availability and actual use of small generation and load units, aggregated estimate data may be used.
2017/09/25
Committee: ITRE
Amendment 1363 #
Proposal for a regulation
Article 49 – paragraph 1
Distribution system operators which are not part of a vertically integrated undertaking or which are unbundled according to the provisions of Article 35 [recast of Directive 2009/72/EC as proposed by COM(2016) 864/2], shall cooperate at Union level through a European Entity for Distribution system operators ("EU DSO entity"), in order to promote the completion and functioning of the internal market in electricity, and to promote optimal management and a coordinated operation of distribution and transmission systems. Distribution system operators who wish to participate in the EU DSO entity shall become registered members of the entity.
2017/09/25
Committee: ITRE
Amendment 1373 #
Proposal for a regulation
Article 49 – paragraph 1 a (new)
The DSOs of each country shall be given the opportunity to elect a country DSO- representative responsible for coordinating inputs, nominating experts to working groups and voting.
2017/09/25
Committee: ITRE
Amendment 1374 #
Proposal for a regulation
Article 49 – paragraph 1 b (new)
The weighting of votes between country DSO-representatives shall be in accordance with the voting procedure of the Council as defined in the consolidated Treaty of the European Union Article 16 (4), as amended by the Treaty of Lisbon (“double majority”).
2017/09/25
Committee: ITRE
Amendment 1379 #
Proposal for a regulation
Article 50 – paragraph –1 (new)
-1. Within [OP: two months after entry into force], each Member State shall ensure that the Member States’ distribution system operators are given the opportunity to elect a country DSO- representative for the EU DSO entity in a fair and transparent manner. The Member State shall ensure that the representative is re-elected every second year and on request of a majority of the Member States’ distribution system operators.
2017/09/25
Committee: ITRE
Amendment 1384 #
Proposal for a regulation
Article 50 – paragraph 1
1. By [OP: twelve months after entry into force], the distribution system operatorcountry DSO- representatives, with the administrative support of the Agency, shall submit to the Commission and to the Agency the draft statutes, a list of registered members, the draft rules of procedure, including the rules of procedures on the consultation with ENTSO for Electricity and other stakeholders and the financing rules, of the EU DSO entity to be established.
2017/09/25
Committee: ITRE
Amendment 1387 #
Proposal for a regulation
Article 50 – paragraph 2
2. Within two months of receipt, the Agency, after formally consulting the organisations representing all stakeholders, in particular distribution system users, shall provide an opinion to the Commission on the draft statutes, the list of members and the draft rules of procedure, taking into account in particular the rules related to the independence of the EU DSO entity from its members, to the prevention of conflicts of interests, and to the necessity to ensure geographically- balanced representation and equitable treatment between its Members, in particular for small or independent Distribution system operators.
2017/09/25
Committee: ITRE
Amendment 1399 #
Proposal for a regulation
Article 50 – paragraph 6
6. The costs related to the activities of the EU DSO entity shall be borne by all European distribution system operators who are registered members and shall be taken into account in the calculation of tariffs. Regulatory authorities shall approve those costs only if they are reasonable and proportionate.
2017/09/25
Committee: ITRE
Amendment 1422 #
Proposal for a regulation
Article 51 – paragraph 1 – point d
(d) digitalisation of distribution networks including deployment of smart grids and intelligensmart metering systems ;
2017/09/25
Committee: ITRE
Amendment 1423 #
Proposal for a regulation
Article 51 – paragraph 1 – point e
(e) data managementguarantee non-discriminatory and neutral access to data regardless of the data management model, and promote standardization, cross-border data exchange, in particular with ENTSO for Electricity where relevant to facilitate data exchange, cyber security and data protection;
2017/09/25
Committee: ITRE
Amendment 1432 #
Proposal for a regulation
Article 51 – paragraph 2 – point a
(a) cooperate effectively with ENTSO for electricity on the monitoring, the Agency and national regulators to facilitate the monitoring by the Agency and where relevant the national regulatory authorities of implementation of the network codes and guidelines which are relevant to the operation and planning of distribution grids and the coordinated operation of the transmission and distribution networks and which are adopted pursuant to this Regulation;
2017/09/25
Committee: ITRE
Amendment 1481 #
Proposal for a regulation
Article 55 – paragraph 1 – point n
(n) demand response, including aggregation, energy storage, and demand curtailment rules;
2017/09/25
Committee: ITRE
Amendment 1482 #
Proposal for a regulation
Article 55 – paragraph 1 – point n a (new)
(n a) energy storage ;
2017/09/25
Committee: ITRE
Amendment 1490 #
Proposal for a regulation
Article 55 – paragraph 2
2. The Commission shall, after consulting the Agency, the ENTSO for Electricity and the other relevant stakeholders, establish a priority list every three years, identifying the areas set out in paragraph 1 to be included in the development of network codes. If the subject-matter of the network code is directly related to the operation of the distribution system and less relevant for the transmission system, the Commission may require the EU DSO entity for electricity instead of the ENTSO for Electricity to convene a drafting committee and submit a proposal for a network code to the agency. The EU DSO entity shall ensure that the drafting committee convened has a geographically-balanced representation, including small or independent distribution system operators and is subject to rules related to independence and the prevention of conflict of interests.
2017/09/25