5 Amendments of Rachida DATI related to 2011/0300(COD)

Amendment 317 #
Proposal for a regulation
Article 4 – paragraph 2 – point c – introductory part
(c) concerning electricity or gas smart grid projects falling under the category set out in point 1(e) of Annex II, the project shall contribute significantly to the following specific functions:
2012/05/08
Committee: ITRE
Amendment 383 #
Proposal for a regulation
Article 5 – paragraph 6 – introductory part
6. If the commissioning of a project of common interest is delayed by more than two years compared to the implementation plan without sufficient justificationfor reasons linked to the poor implementation of the project by the developer:
2012/05/08
Committee: ITRE
Amendment 407 #
Proposal for a regulation
Article 5 – paragraph 6 a (new)
(6a) If the commissioning of a project of common interest is delayed by more than two years compared to the implementation plan for reasons outside the developer’s control, the parties may renegotiate the project timetable, subject to approval by the Commission.
2012/05/08
Committee: ITRE
Amendment 602 #
Proposal for a regulation
Article 15 – paragraph 2 – point b
(b) the project is commercially not viable according to the business plan and other assessments carried out, notably by possible investors or creditors. The decision on incentives and its justification referred to in paragraph 3 of Article 14 shall be taken into account when assessing the project's commercial viability; if several commercially non-viable projects are in competition, all the costs and benefits of each project should be compared and the one which offers the best cost-benefit ratio should be chosen; and
2012/05/08
Committee: ITRE
Amendment 671 #
Proposal for a regulation
Annex I – part 4 – point 10 – paragraph 1
(10) Smart grids deployment: adoption of smart grid technologies across the Union to efficiently integrate the behaviour and actions of all users connected to the electricity and gas network, in particular the generation of large amounts of electricity and gas from renewable or distributed energy sources and demand response by consumers;
2012/05/08
Committee: ITRE