2022/0211(BUD) Amending budget 4/2022: update of revenue (own resources) and other technical adjustments

Progress: Procedure completed

RoleCommitteeRapporteurShadows
Lead BUDG RESSLER Karlo (icon: EPP EPP) NEGRESCU Victor (icon: S&D S&D), ŞTEFĂNUȚĂ Nicolae (icon: Renew Renew), HAHN Henrike (icon: Verts/ALE Verts/ALE), RZOŃCA Bogdan (icon: ECR ECR), PAPADIMOULIS Dimitrios (icon: GUE/NGL GUE/NGL)
Lead committee dossier:

Events

2022/12/05
   Final act published in Official Journal
2022/10/19
   EP - Results of vote in Parliament
2022/10/19
   EP - Decision by Parliament
Details

The European Parliament adopted by 593 votes to 16, with 12 abstentions, a resolution approving the Council's position on draft amending budget No 4/2022 of the European Union for the financial year 2022.

The main purpose of draft amending budget (DAB) No 4/2022 is to update the revenue side of the budget to take account of recent developments, namely the updated forecast of own resources for the 2022 budget, approved by the advisory committee on own resources (ACOR) on 23 May 2022, and the update of other revenues such as the UK contribution, fines and others.

The DAB also includes two specific expenditure-related adjustments corresponding to an adaptation of the budget nomenclature following the Commission proposal of 18 May 2022 on REPowerEU and the extension of Eurojust's mandate to collect and preserve evidence of war crimes.

No additional commitment or payment appropriations are required.

Highlighting the increase in genuine own resources of EUR 3 573.9 million, Parliament called for the introduction of new own resources to be accelerated so that the additional revenue from new own resources would be sufficient to cover at least the repayment of costs of the Recovery Instrument.

Members regretted that, in spite of Parliament's insistence, the Commission had decided to present elements related to the update of revenue with other elements related to ongoing negotiations. To better respect the prerogative of the budgetary authority , Members considered that the Commission should present a draft amending budget for one purpose only and refrain from combining several purposes in one draft amending budget.

Parliament welcomed the swift adoption of Regulation (EU) 2022/838 to extend Eurojust's mandate to support Ukraine in collecting, preserving and analysing evidence of war crimes following Russia's brutal and unjustified aggression. However, Members objected to the intended use of internal redeployments within the same policy area later in the year to finance the posts proposed under this draft amending budget. They stressed, in this context, that there are sufficient margins under Heading 2b.

Parliament also reaffirmed its long-standing position that increasing tasks and responsibilities for agencies must be accompanied by corresponding levels of fresh resources.

Documents
2022/10/11
   EP - Budgetary report tabled for plenary, 1st reading
Documents
2022/10/11
   EP - Budgetary report tabled for plenary
Documents
2022/10/10
   EP - Vote in committee
2022/10/03
   EP - Committee referral announced in Parliament
2022/09/26
   EP - Amendments tabled in committee
Documents
2022/09/20
   CSL - Council position on draft budget
Details

The Council adopted its position on the draft amending budget No 4 to the general budget for 2022: entering the surplus of the financial year 2021.

As a reminder, on 1 July 2022, the Commission submitted to the Council draft amending budget (DAB) No 4 to the general budget for 2022 which aims to update the revenue side of the budget to take account of the latest developments: (i) the updated own resources forecasts for the budget 2022 agreed by the Advisory Committee on Own Resources (ACOR) on 23 May 2022; (ii) to update other revenues such as the United Kingdom contribution, fines and other.

In addition, DAB No 4/2022 includes two specific adjustments related to expenditure:

- adjustment of the budgetary nomenclature following the new possibilities for Member States to transfer resources of their initial European Regional Development Fund (ERDF), Cohesion Fund (CF), European Social Fund Plus (ESF+) and European Maritime, Fisheries and Aquaculture Fund (EMFAF) allocations to the REPowerEU chapter of the Recovery and Resilience Facility (RRF) following the Commission proposal for REPowerEU on 18 May 2022;

- the additional staff requested for Eurojust following the extension of its mandate to collect and preserve war crime evidence.

The related appropriations in 2022 will be financed through internal redeployment, and therefore no additional financing is required for this purpose.

On 20 September 2022, the Council adopted its position on DAB No 4 to the general budget for 2022 as set out in the technical annex to its explanatory memorandum.

Documents
2022/09/20
   CSL - Draft budget approved by Council
2022/09/19
   CSL - Council position on draft budget published
Details

The Council adopted its position on the draft amending budget No 4 to the general budget for 2022: entering the surplus of the financial year 2021.

As a reminder, on 1 July 2022, the Commission submitted to the Council draft amending budget (DAB) No 4 to the general budget for 2022 which aims to update the revenue side of the budget to take account of the latest developments: (i) the updated own resources forecasts for the budget 2022 agreed by the Advisory Committee on Own Resources (ACOR) on 23 May 2022; (ii) to update other revenues such as the United Kingdom contribution, fines and other.

In addition, DAB No 4/2022 includes two specific adjustments related to expenditure:

- adjustment of the budgetary nomenclature following the new possibilities for Member States to transfer resources of their initial European Regional Development Fund (ERDF), Cohesion Fund (CF), European Social Fund Plus (ESF+) and European Maritime, Fisheries and Aquaculture Fund (EMFAF) allocations to the REPowerEU chapter of the Recovery and Resilience Facility (RRF) following the Commission proposal for REPowerEU on 18 May 2022;

- the additional staff requested for Eurojust following the extension of its mandate to collect and preserve war crime evidence.

The related appropriations in 2022 will be financed through internal redeployment, and therefore no additional financing is required for this purpose.

On 20 September 2022, the Council adopted its position on DAB No 4 to the general budget for 2022 as set out in the technical annex to its explanatory memorandum.

Documents
2022/07/13
   EP - Committee draft report
Documents
2022/07/01
   EC - Commission draft budget published
Details

PURPOSE: to present Draft Amending Budget (DAB) No. 4 to the General Budget 2022 - Update of revenue (own resources) and other technical adjustments.

CONTENT: the main purpose of DAB 4 for the year 2022 is to update the revenue side of the budget to take account of recent developments.

Update of revenue

The adjustments to the revenue side of the budget are necessary to update the estimates for traditional own resources (TOR) as well as for own resources based on value added tax (VAT), non-recycled plastic packaging waste (PPW) and gross national income (GNI) , taking into account the spring economic forecast.

The Commission proposes to revise the financing of the budget on the basis of more recent economic forecasts. This revision concerns the forecasts for the TOR to be paid into the budget in 2022, as well as the forecasts for the VAT, PPW and GNI bases in 2022.

The economic scenario underlying the 2022 budget is broadly confirmed by the latest estimates:

- total customs duties to be collected in 2022, net of 25 % collection costs, are forecast at EUR 20 479.8 million , which represents an increase of 14.3 % compared with the forecast of EUR 17 912.6 million included in the 2022 budget;

- the total 2022 EU uncapped VAT base is now forecast at EUR 6 588 601.0 million , which represents an increase of 3.2 % compared to the May 2021 forecast of EUR 6 384 062.6 million. The total 2022 EU capped VAT base is forecast at EUR 6 571 411.1 million, which represents an increase of 3.4 % compared to the May 2021 forecast of EUR 6 357 129.3 million;

- the forecast of non-recycled plastic packaging waste in the EU amounts to EUR 8 840 522.1 tonnes in 2022 , which is an increase of 5.4 % compared to the May 2021 forecast of 8 388 536.2 tonnes. The corresponding Member States contributions from the plastic packaging waste is presented the accompanying budgetary annex;

- the total 2022 EU GNI base is forecast at EUR 15 493 666.4 million , which is an increase of 4.2 % compared to the May 2021 forecast of EUR 14 874 288.2 million.

Other revenue

In addition, the amount of other revenue is updated to take into account the revised UK contribution , the fines and periodic penalty payments definitively collected until June 2022, as well as the contribution of the European Coal and Steel Community (ECSC) in respect of the reimbursement to the UK of its share of the net assets.

- the UK contribution is based on the UK share, which is calculated as the ratio between the own resources made available by the United Kingdom in the years 2014 to 2020 and the own resources made available during that period by all Member States including the United Kingdom. The United Kingdom’s share was adjusted in 2022 in accordance with the Withdrawal Agreement. The definitive share of the United Kingdom has been set at 12,431681219587700 %;

- EUR 440.5 million in fines and periodic penalty payments were collected between 1 January and 1 June 2022. In accordance with the provisions of the withdrawal agreement, the United Kingdom is entitled to receive its share of EUR 281 million. It is therefore proposed to increase the initial forecast of EUR 101 million entered in the 2022 budget by EUR 339.5 million .

Update of expenditure

Additionally, DAB 4/2022 includes two specific adjustments related to expenditure:

- adjustment of the budgetary nomenclature following the new possibilities for Member States to transfer resources of their initial European Regional Development Fund (ERDF), Cohesion Fund (CF), European Social Fund Plus (ESF+) and European Maritime, Fisheries and Aquaculture Fund (EMFAF) allocations to the REPowerEU chapter of the Recovery and Resilience Facility (RRF) following the Commission proposal for REPowerEU on 18 May 2022;

- the additional staff requested for Eurojust following the extension of its mandate to collect and preserve war crime evidence 8 . The related appropriations in 2022 will be financed through internal redeployment, and therefore no additional financing is required for this purpose.

No additional commitment and payment appropriations are requested under the 2022 budget. The revenue side of the budget is proposed to be adjusted as set out in this DAB 4/2022.

2022/06/23
   EP - RESSLER Karlo (EPP) appointed as rapporteur in BUDG

Documents

Votes

Projet de budget rectificatif nº 4 au budget général 2022: Actualisation des recettes (ressources propres) et autres ajustements techniques - Draft amending budget 4/2022: Update of revenue (own resources) and other technical adjustments - Entwurf des Berichtigungshaushaltsplans Nr. 472022: Aktualisierung der Einnahmen (Eigenmittel) und sonstige technische Anpassungen - A9-0240/2022 - Karlo Ressler - Proposition de résolution #

2022/10/19 Outcome: +: 593, -: 16, 0: 12
DE FR IT PL ES RO NL SE BG CZ HU FI PT BE AT LT IE EL HR SK DK LV SI MT CY LU EE ??
Total
83
71
62
49
53
32
27
20
16
20
15
14
18
18
19
11
11
14
12
11
8
7
7
5
5
5
7
1
icon: PPE PPE
158

Hungary PPE

1

Denmark PPE

For (1)

1

Latvia PPE

2

Malta PPE

For (1)

1
2

Luxembourg PPE

2

Estonia PPE

For (1)

1
icon: S&D S&D
136

Czechia S&D

For (1)

1

Lithuania S&D

2

Greece S&D

For (1)

1

Slovakia S&D

For (1)

1

Latvia S&D

2

Slovenia S&D

For (1)

1

Cyprus S&D

2

Luxembourg S&D

For (1)

1

Estonia S&D

2
icon: Renew Renew
93

Italy Renew

2

Poland Renew

1
3

Hungary Renew

For (1)

1

Finland Renew

3

Austria Renew

For (1)

1

Lithuania Renew

1

Ireland Renew

2

Greece Renew

1

Croatia Renew

For (1)

1

Latvia Renew

For (1)

1

Slovenia Renew

2

Luxembourg Renew

For (1)

1

Estonia Renew

3
icon: Verts/ALE Verts/ALE
66

Italy Verts/ALE

3

Poland Verts/ALE

For (1)

1

Netherlands Verts/ALE

2

Sweden Verts/ALE

3

Czechia Verts/ALE

3

Finland Verts/ALE

3

Portugal Verts/ALE

1

Belgium Verts/ALE

2

Austria Verts/ALE

3

Lithuania Verts/ALE

2

Ireland Verts/ALE

2

Denmark Verts/ALE

For (1)

1

Luxembourg Verts/ALE

For (1)

1
icon: ECR ECR
59

Romania ECR

1

Netherlands ECR

Against (1)

5

Sweden ECR

For (1)

3

Bulgaria ECR

2

Lithuania ECR

1

Greece ECR

1

Croatia ECR

1

Slovakia ECR

For (1)

1

Latvia ECR

For (1)

1
icon: ID ID
52

Czechia ID

Against (2)

2

Finland ID

2

Belgium ID

2

Austria ID

3

Estonia ID

Against (1)

1
icon: The Left The Left
29

Netherlands The Left

Abstain (1)

1

Sweden The Left

For (1)

1

Czechia The Left

1

Finland The Left

For (1)

1

Portugal The Left

Against (1)

3

Belgium The Left

Abstain (1)

1

Ireland The Left

2

Cyprus The Left

1
icon: NI NI
28

Germany NI

For (1)

1

France NI

For (1)

1

Lithuania NI

1

Greece NI

2

Croatia NI

Against (1)

Abstain (1)

2

Slovakia NI

Against (1)

1

Latvia NI

1

NI

For (1)

1
AmendmentsDossier
2 2022/0211(BUD)
2022/09/27 BUDG 2 amendments...
source: 735.528

History

(these mark the time of scraping, not the official date of the change)

events/6
date
2022-10-19T00:00:00
type
Results of vote in Parliament
body
EP
docs
url: https://oeil.secure.europarl.europa.eu/oeil/popups/sda.do?id=58900&l=en title: Results of vote in Parliament
events/7
date
2022-12-05T00:00:00
type
Final act published in Official Journal
procedure/final
title
OJ L 313 05.12.2022, p. 0001
url
https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=OJ:L:2022:313:TOC
procedure/stage_reached
Old
Procedure completed, awaiting publication in Official Journal
New
Procedure completed
procedure/title
Old
Draft amending budget 4/2022: update of revenue (own resources) and other technical adjustments
New
Amending budget 4/2022: update of revenue (own resources) and other technical adjustments
docs/4
date
2022-10-19T00:00:00
docs
url: https://www.europarl.europa.eu/doceo/document/TA-9-2022-0365_EN.html title: T9-0365/2022
type
Budgetary text adopted by Parliament
body
EP
events/6/summary
  • The European Parliament adopted by 593 votes to 16, with 12 abstentions, a resolution approving the Council's position on draft amending budget No 4/2022 of the European Union for the financial year 2022.
  • The main purpose of draft amending budget (DAB) No 4/2022 is to update the revenue side of the budget to take account of recent developments, namely the updated forecast of own resources for the 2022 budget, approved by the advisory committee on own resources (ACOR) on 23 May 2022, and the update of other revenues such as the UK contribution, fines and others.
  • The DAB also includes two specific expenditure-related adjustments corresponding to an adaptation of the budget nomenclature following the Commission proposal of 18 May 2022 on REPowerEU and the extension of Eurojust's mandate to collect and preserve evidence of war crimes.
  • No additional commitment or payment appropriations are required.
  • Highlighting the increase in genuine own resources of EUR 3 573.9 million, Parliament called for the introduction of new own resources to be accelerated so that the additional revenue from new own resources would be sufficient to cover at least the repayment of costs of the Recovery Instrument.
  • Members regretted that, in spite of Parliament's insistence, the Commission had decided to present elements related to the update of revenue with other elements related to ongoing negotiations. To better respect the prerogative of the budgetary authority , Members considered that the Commission should present a draft amending budget for one purpose only and refrain from combining several purposes in one draft amending budget.
  • Parliament welcomed the swift adoption of Regulation (EU) 2022/838 to extend Eurojust's mandate to support Ukraine in collecting, preserving and analysing evidence of war crimes following Russia's brutal and unjustified aggression. However, Members objected to the intended use of internal redeployments within the same policy area later in the year to finance the posts proposed under this draft amending budget. They stressed, in this context, that there are sufficient margins under Heading 2b.
  • Parliament also reaffirmed its long-standing position that increasing tasks and responsibilities for agencies must be accompanied by corresponding levels of fresh resources.
docs/4
date
2022-10-19T00:00:00
docs
url: https://www.europarl.europa.eu/doceo/document/TA-9-2022-0365_EN.html title: T9-0365/2022
type
Budgetary text adopted by Parliament
body
EP
events/6
date
2022-10-19T00:00:00
type
Decision by Parliament
body
EP
docs
url: https://www.europarl.europa.eu/doceo/document/TA-9-2022-0365_EN.html title: T9-0365/2022
forecasts
  • date: 2022-10-19T00:00:00 title: Vote in plenary scheduled
procedure/stage_reached
Old
Awaiting Parliament's position on the draft budget
New
Procedure completed, awaiting publication in Official Journal
docs/3/docs/0/url
https://www.europarl.europa.eu/doceo/document/A-9-2022-0240_EN.html
events/5/docs/0/url
https://www.europarl.europa.eu/doceo/document/A-9-2022-0240_EN.html
docs/3
date
2022-10-11T00:00:00
docs
title: A9-0240/2022
type
Budgetary report tabled for plenary, 1st reading
body
EP
events/2
date
2022-09-20T00:00:00
type
Draft budget approved by Council
body
CSL
events/4
date
2022-10-10T00:00:00
type
Vote in committee
body
EP
events/5
date
2022-10-11T00:00:00
type
Budgetary report tabled for plenary
body
EP
docs
title: A9-0240/2022
forecasts/0
date
2022-10-19T00:00:00
title
Vote in plenary scheduled
forecasts/0
date
2022-10-17T00:00:00
title
Indicative plenary sitting date
procedure/Other legal basis
Rules of Procedure EP 159
procedure/stage_reached
Old
Awaiting committee decision
New
Awaiting Parliament's position on the draft budget
events/2
date
2022-10-03T00:00:00
type
Committee referral announced in Parliament
body
EP
procedure/dossier_of_the_committee
  • BUDG/9/09418
procedure/stage_reached
Old
Preparatory phase in Parliament
New
Awaiting committee decision
docs/1/summary
  • The Council adopted its position on the draft amending budget No 4 to the general budget for 2022: entering the surplus of the financial year 2021.
  • As a reminder, on 1 July 2022, the Commission submitted to the Council draft amending budget (DAB) No 4 to the general budget for 2022 which aims to update the revenue side of the budget to take account of the latest developments: (i) the updated own resources forecasts for the budget 2022 agreed by the Advisory Committee on Own Resources (ACOR) on 23 May 2022; (ii) to update other revenues such as the United Kingdom contribution, fines and other.
  • In addition, DAB No 4/2022 includes two specific adjustments related to expenditure:
  • - adjustment of the budgetary nomenclature following the new possibilities for Member States to transfer resources of their initial European Regional Development Fund (ERDF), Cohesion Fund (CF), European Social Fund Plus (ESF+) and European Maritime, Fisheries and Aquaculture Fund (EMFAF) allocations to the REPowerEU chapter of the Recovery and Resilience Facility (RRF) following the Commission proposal for REPowerEU on 18 May 2022;
  • - the additional staff requested for Eurojust following the extension of its mandate to collect and preserve war crime evidence.
  • The related appropriations in 2022 will be financed through internal redeployment, and therefore no additional financing is required for this purpose.
  • On 20 September 2022, the Council adopted its position on DAB No 4 to the general budget for 2022 as set out in the technical annex to its explanatory memorandum.
events/1/summary
  • The Council adopted its position on the draft amending budget No 4 to the general budget for 2022: entering the surplus of the financial year 2021.
  • As a reminder, on 1 July 2022, the Commission submitted to the Council draft amending budget (DAB) No 4 to the general budget for 2022 which aims to update the revenue side of the budget to take account of the latest developments: (i) the updated own resources forecasts for the budget 2022 agreed by the Advisory Committee on Own Resources (ACOR) on 23 May 2022; (ii) to update other revenues such as the United Kingdom contribution, fines and other.
  • In addition, DAB No 4/2022 includes two specific adjustments related to expenditure:
  • - adjustment of the budgetary nomenclature following the new possibilities for Member States to transfer resources of their initial European Regional Development Fund (ERDF), Cohesion Fund (CF), European Social Fund Plus (ESF+) and European Maritime, Fisheries and Aquaculture Fund (EMFAF) allocations to the REPowerEU chapter of the Recovery and Resilience Facility (RRF) following the Commission proposal for REPowerEU on 18 May 2022;
  • - the additional staff requested for Eurojust following the extension of its mandate to collect and preserve war crime evidence.
  • The related appropriations in 2022 will be financed through internal redeployment, and therefore no additional financing is required for this purpose.
  • On 20 September 2022, the Council adopted its position on DAB No 4 to the general budget for 2022 as set out in the technical annex to its explanatory memorandum.
docs/2
date
2022-09-26T00:00:00
docs
url: https://www.europarl.europa.eu/doceo/document/BUDG-AM-735528_EN.html title: PE735.528
type
Amendments tabled in committee
body
EP
docs/1
date
2022-09-20T00:00:00
docs
title: 12623/2022
type
Council position on draft budget
body
CSL
events/1
date
2022-09-19T00:00:00
type
Council position on draft budget published
body
CSL
docs
title: 12623/2022
commission
  • body: EC dg: Budget commissioner: HAHN Johannes
forecasts
  • date: 2022-10-17T00:00:00 title: Indicative plenary sitting date
committees/0/shadows/3
name
LAPORTE Hélène
group
Identity and Democracy
abbr
ID
docs/0
date
2022-07-01T00:00:00
docs
type
Commission draft budget
body
EC
events/0/summary
  • PURPOSE: to present Draft Amending Budget (DAB) No. 4 to the General Budget 2022 - Update of revenue (own resources) and other technical adjustments.
  • CONTENT: the main purpose of DAB 4 for the year 2022 is to update the revenue side of the budget to take account of recent developments.
  • Update of revenue
  • The adjustments to the revenue side of the budget are necessary to update the estimates for traditional own resources (TOR) as well as for own resources based on value added tax (VAT), non-recycled plastic packaging waste (PPW) and gross national income (GNI) , taking into account the spring economic forecast.
  • The Commission proposes to revise the financing of the budget on the basis of more recent economic forecasts. This revision concerns the forecasts for the TOR to be paid into the budget in 2022, as well as the forecasts for the VAT, PPW and GNI bases in 2022.
  • The economic scenario underlying the 2022 budget is broadly confirmed by the latest estimates:
  • - total customs duties to be collected in 2022, net of 25 % collection costs, are forecast at EUR 20 479.8 million , which represents an increase of 14.3 % compared with the forecast of EUR 17 912.6 million included in the 2022 budget;
  • - the total 2022 EU uncapped VAT base is now forecast at EUR 6 588 601.0 million , which represents an increase of 3.2 % compared to the May 2021 forecast of EUR 6 384 062.6 million. The total 2022 EU capped VAT base is forecast at EUR 6 571 411.1 million, which represents an increase of 3.4 % compared to the May 2021 forecast of EUR 6 357 129.3 million;
  • - the forecast of non-recycled plastic packaging waste in the EU amounts to EUR 8 840 522.1 tonnes in 2022 , which is an increase of 5.4 % compared to the May 2021 forecast of 8 388 536.2 tonnes. The corresponding Member States contributions from the plastic packaging waste is presented the accompanying budgetary annex;
  • - the total 2022 EU GNI base is forecast at EUR 15 493 666.4 million , which is an increase of 4.2 % compared to the May 2021 forecast of EUR 14 874 288.2 million.
  • Other revenue
  • In addition, the amount of other revenue is updated to take into account the revised UK contribution , the fines and periodic penalty payments definitively collected until June 2022, as well as the contribution of the European Coal and Steel Community (ECSC) in respect of the reimbursement to the UK of its share of the net assets.
  • - the UK contribution is based on the UK share, which is calculated as the ratio between the own resources made available by the United Kingdom in the years 2014 to 2020 and the own resources made available during that period by all Member States including the United Kingdom. The United Kingdom’s share was adjusted in 2022 in accordance with the Withdrawal Agreement. The definitive share of the United Kingdom has been set at 12,431681219587700 %;
  • - EUR 440.5 million in fines and periodic penalty payments were collected between 1 January and 1 June 2022. In accordance with the provisions of the withdrawal agreement, the United Kingdom is entitled to receive its share of EUR 281 million. It is therefore proposed to increase the initial forecast of EUR 101 million entered in the 2022 budget by EUR 339.5 million .
  • Update of expenditure
  • Additionally, DAB 4/2022 includes two specific adjustments related to expenditure:
  • - adjustment of the budgetary nomenclature following the new possibilities for Member States to transfer resources of their initial European Regional Development Fund (ERDF), Cohesion Fund (CF), European Social Fund Plus (ESF+) and European Maritime, Fisheries and Aquaculture Fund (EMFAF) allocations to the REPowerEU chapter of the Recovery and Resilience Facility (RRF) following the Commission proposal for REPowerEU on 18 May 2022;
  • - the additional staff requested for Eurojust following the extension of its mandate to collect and preserve war crime evidence 8 . The related appropriations in 2022 will be financed through internal redeployment, and therefore no additional financing is required for this purpose.
  • No additional commitment and payment appropriations are requested under the 2022 budget. The revenue side of the budget is proposed to be adjusted as set out in this DAB 4/2022.
docs/1/docs/0/url
https://www.europarl.europa.eu/doceo/document/BUDG-PR-734370_EN.html
docs/1
date
2022-07-13T00:00:00
docs
title: PE734.370
type
Committee draft report
body
EP